Skip to main content

Below is an anticipated timeline for the proposed development, we are keen to move quickly given the demand for logistic space in the local area.

Following careful consideration of the responses received through the public consultation, as well as discussions with key stakeholders and Hertsmere Borough Council, we hope to work towards the proposed timeline below.

July 2023

Submission of original application based on maximum of 45,000sqm development parameter

May 2024

Resolution to grant outline planning permission subject to maximum development parameter of 30,000sqm

Summer 2024

Completion of legal agreement and decision notice

Summer 2024

Submission of new application seeking outline planning permission for up to 45,000sqm (not 40k as per current draft)

Winter 2024

Expected determination of new application

Winter 2024

Submission of a reserved matters application which will cover the finer details of the proposals including design

Spring 2025

Expected determination of reserved matters

Summer 2025

Commencement of construction work

Summer 2026

Completion of development

Have your say

We would like to hear from the local community
Share your thoughts on our proposals for land north east of Elton Way, Watford, by completing our online survey.

Start the survey

If you have any questions, feedback or wish to be kept in touch please contact us using the information below:

Call: 0800 148 8911
Email: info@eltonway-consultation.co.uk
Write: Freepost MEETING PLACE CONSULTATION (no stamp required)

Close